NTPC informs about outcome of board meeting
NTPC informed that the Board of Directors of NTPC Limited (NTPC) in its meeting held on March 28, 2026 has, inter-alia, approved the Investment proposal for Battery Energy Storage System (BESS) with a total capacity of 4.70 GWh, at an estimated project cost of Rs.5,821.90 Crore and additional equity commitment of Rs 3,173.67 Crore in Meja Urja Nigam Private (MUNPL), the Joint Venture Company of NTPC and Uttar Pradesh Rajya Vidyut Utpadan Nigam (UPRVUNL), for setting up Meja Super Thermal Power Project Stage-II (3x800 MW). With this investment, the total equity commitment in MUNPL would reach to Rs.5,000 Crore. The release of additional equity will be subjected to receipt of proportionate equity contribution from UPRVUNL.
The above information is a part of company’s filings submitted to BSE.