Swelect Energy commissions newly erected 110/33 KV Pooling Sub Station in Tamil Nadu
The company has introduced 1 X 50 MVA, 110/33 KV Power Transformer for 110 KV connectivity at Sirungattur 110/33-11 KV Substation
Swelect Energy Systems has commissioned newly erected 110/33 KV Pooling Sub Station (PSS) at Sirungattur, Tiruvanamalai, Tamil Nadu on April 16, 2026. The company has introduced 1 X 50 MVA, 110/33 KV Power Transformer for 110 KV connectivity at Sirungattur 110/33-11 KV Substation for evacuation of 50 MW Solar Power project in Villupuram Operation Circle.
Swelect Energy Systems (formerly known as Numeric Power Systems) is a leader in delivering high-performance solar, wind, energy storage and power electronic solutions.