ACME Solar Holdings’ arm commissions sixth phase of 38 MW of BESS project in Rajasthan

ACME Suryodaya has achieved a commissioned capacity of 285 MW / 601.904 MWh

ACME Solar Holdings (ASHL), through its wholly owned subsidiary -- ACME Suryodaya has commissioned the sixth phase of 38 MW / 80.252 MWh capacity of Battery Energy Storage System (BESS) Project located at Jaisalmer, Rajasthan, on April 13, 2026. The Commercial operation date (COD) for the stated phase–VI shall be April 15, 2026. 

With this, ACME Suryodaya has achieved a commissioned capacity of 285 MW / 601.904 MWh.

ACME Solar Holdings is one of India’s leading renewable energy independent power producers (IPP). The company develop, build, own, and operate large-scale clean energy solutions.